Client : Ogero

Location: Ras Beirut, Bir Hassan

Description:

Complete installation and commissioning of two Ogero Data Centers.

Scope of Work: 
Liebert Precesion Cooling units  (N+N) 50KW HPM+ CRAC

DC system  :

  • (Environmental monitoring system for humidity, temperature, water detection)
  • Access Control
  • Fire Suppression (FM200)

Electrical works.Raised Floor, Fire rated door,Civil Works,Turnkey solution

First phase of 15 racks with provision for expansion. 
Commissioning all the infrastructure equipment with upgrade.